Refer to Appendix 2 and lines 53–57. Calculate:
- (a)Refer to Appendix 2 and lines 53–57. Calculate:[8]
- (a)(i)the change in capacity utilisation which will result if the special order is accepted[4]
- (a)(ii)the change to CSP's profits if the special order is accepted.[4]
- (b)Refer to your results from 4(a) and any other information. Recommend whether CSP should accept the special order from X Tours.[12]
This question uses a diagram from the original paper, which isn't shown here. Open the full paper from the past papers archive to see it.
Mark scheme
Marking points from the official mark scheme (Oct/Nov 2019). The mark or mark type is shown in brackets.
- [1] Formula for Capacity Utilisation: current capacity / maximum capacity × 100
- [1] Calculation of Current Capacity Utilisation: 32000 / 44000 × 100 = 72.7%
- [1] Calculation of New Capacity Utilisation with special order: 42000 / 44000 × 100 = 95.45%
- [1] Change in Capacity Utilisation: 22.8% points (allow range 22-23% or 31.4% change relative to current CU)
- [1] Total contribution = contribution per unit × extra output for special order OR Contribution per unit = selling price – variable cost per unit
- [1] Variable unit cost = $4 + $1 + $1.50 = $6.50
- [1] Contribution per unit = $7 – $6.50 = $0.50
- [1] Total contribution = $0.50 × 10000 = $5000 (change to profits)
- [1] Meaning of capacity utilisation and why it is important
- [1] Meaning of total contribution and importance in profit calculations
- [1] Relevant points about special orders
- [1] Reference to results (e.g., increase in CU from 72.7% to 95.45%, profit increase of $5000)
- [1] Application of changes to capacity and profits in context of CSP
- [1] Reference to other points from the text, including nature of special order (e.g. X Tours, 10,000 lamps, $7 per lamp)
- [1] Reasons for and against acceptance of special order
- [1] For acceptance: addition to profit, better use of resources, could lead to more orders in future.
- [1] Against acceptance: capacity utilisation over 95%, no spare capacity for other orders that may be at full price, will it dilute present sales of lamps from other retailers?
- [1] If another order comes in this will put the company over capacity
- [1] Accept or decline order?
- [1] Short/long term impacts?
- [1] Is it a 'one off' order?
- [1] Management objectives?
Write your answer and get it marked