Refer to lines 29–31. Calculate the forecast capacity utilisation for 2020 in FE's factory.
- (a)Refer to lines 29–31. Calculate the forecast capacity utilisation for 2020 in FE's factory.[2]
- (b)Refer to Table 1. Calculate the difference in unit cost of towers produced by expanding the factory or outsourcing.[3]
- (c)Refer to your results from 2(a) and 2(b) and other information. Recommend to FE's directors whether to outsource production of the towers.[12]
Mark scheme
Marking points from the official mark scheme (Feb/Mar 2020). The mark or mark type is shown in brackets.
- [1] CU = (Current output / Capacity) x100
- [1] Or Forecast output / capacity x100
- [2] CU = 425 / 450 x100 = 94.4%
- [1] 94.4
- [1] Unit cost if factory extension 0.02 + 0.33 = ($)0.35 (m)
- [1] Unit cost if outsourcing 0.37 + 0.01 = ($)0.38 (m)
- [1] Difference = $0.03 m or $30 000
- [2] 0.03 or 30 000
- [2] Possible answers with working (Deduct further mark if no $ or m) $0.02 m
- [2] $0.05 m
- [1] $0.04 m
- [K] Definition of outsourcing: when a business contracts out activity to a third party
- [K] Key factors in decision: reliability of outsourcing company, impact on quality, relative cost, time period
- [APP] Capacity utilisation is already 94.4% so hard to increase production further
- [APP] Cost of outsourcing is $38 000 per unit.
- [APP] Outsourcing is more expensive per unit by $30 000
- [APP] Need for borrowing $150m for factory expansion
- [APP] Expansion increases capacity by 75 more wind turbines relative to outsourcing (675 compared to 600)
- [APP] FE's focus on quality and 100% in-house production
- [APP] Use of difference in timescale - 12 months v 4 months to increase production
- [AN] Any reduction in quality from outsourcing could damage FE's reputation and result in lower sales or impact ability to charge higher prices
- [AN] Extension of the factory may cause a reduction in production in 2020 and impact sales to existing customers.
- [AN] Factory extension will take 12 months therefore may result in being unable to meet 7% increase in demand so loss of sales will result
- [AN] Outsourcing is more flexible so if demand doesn't continue to increase FE can vary contract according to level of demand maintaining a competitive cost per unit
- [AN] Factory extension will increase gearing, increasing costs due to forecast rise in interest rates
- [AN] Outsourcing is more expensive which will increase price or reduce profit margins
- [EVAL] A supported recommendation should follow consideration of pros and cons of outsourcing
- [EVAL] Is FE certain that the costings are accurate?
- [EVAL] Long run v short run consideration. Initially after building extension FE will be operating below capacity thus additional fixed costs will be spread over a lower number of towers. This will increase the cost of in house production above that of outsourcing and thus reduce profit.
- [EVAL] How long will it take to increase sales to use the capacity of the extended factory?
- [EVAL] Will the extension disrupt production of wind turbines to meet existing customer orders?
- [EVAL] Factory extension increases fixed costs significantly due to borrowing and if demand doesn't increase there will be spare capacity resulting in an increase in unit cost
- [EVAL] How long will it take to negotiate contract with CT?