Refer to the network diagram in Fig. 1 and to Table 2 in the Insert.
- (a)(i)Complete the network diagram at nodes 3 and 4.[4]
- (a)(ii)State the activities on the critical path.[1]
- (a)(iii)State the minimum time to complete the opening of the new café.[1]
- (a)(iv)Calculate the free float of Activity F.[2]
- (b)Refer to your answers to 2(a) and any other information. Discuss whether PY's directors should be confident that the café in city X will be open in time for the summer season.[12]
This question uses a diagram from the original paper, which isn't shown here. Open the full paper from the past papers archive to see it.
Mark scheme
Marking points from the official mark scheme (Feb/Mar 2019). The mark or mark type is shown in brackets.
- [4] (a)(i) Node 3: EST = 2 LFT = 2; Node 4: EST = 4 LFT = 7
- [1] (a)(ii) ACEK
- [1] (a)(iii) 9 (weeks)
- [1] (a)(iv) Free float = EST of next activity – duration this activity – EST of this activity
- [1] (a)(iv) 5 – 3 – 2
- [2] (a)(iv) Free float F = 0 (weeks)
- [0] (b) Definition of network analysis: this is part of project management to ensure that resources are used efficiently. Also known as critical path analysis it identifies all tasks in a project, puts them in the correct sequence and allows for the identification of the critical path.
- [0] (b) Planning of when resources are needed and their use can save time
- [0] (b) Sets target to work towards
- [0] (b) Construction of network diagram forces managers to plan project carefully
- [0] (b) Identifies critical activities for management to focus on
- [0] (b) Figures are based on estimates / assumptions so could be unreliable
- [0] (b) Identifies whether new outlet can be opened in time for peak seasonal demand
- [0] (b) 9 weeks minimum time according to the CPA
- [0] (b) 1 week float
- [0] (b) Reference to specific critical activities / aspects of the network e.g. equipment must be delivered by week 6
- [0] (b) 75 cafes so have done this multiple times before
- [0] (b) Some activities depend on external factors such as ordering and delivery of equipment and building work
- [0] (b) Planning of when resources are needed help ensure project is more organised and therefore time is managed more effectively
- [0] (b) Targets set will help motivate staff and increase efficiency therefore more likely to be completed on time
- [0] (b) Construction of network diagram forces managers to plan project carefully and therefore coordinate resources such as HR, Operations and Finance
- [0] (b) Identifies critical activities for management to focus on. Thus, if critical activities are delayed managers can divert resources from non-critical activities to get project back on track
- [0] (b) Figures are based on estimates / assumptions so could be unreliable
- [0] (b) Network presented is relatively simplistic – more detail needed
- [0] (b) Doesn't guarantee that project will be completed on time
- [0] (b) PY has experience of opening many outlets so should be relatively accurate
- [0] (b) Needs to be managed effectively
- [0] (b) No control over external influences e.g. suppliers
- [0] (b) Not much margin for error as only one week float