A-LevelBusiness StudiesOperations management9609/32 · Feb/Mar 2019 · Q220 Marks

Refer to the network diagram in Fig. 1 and to Table 2 in the Insert.

  1. (a)(i)Complete the network diagram at nodes 3 and 4.[4]
  2. (a)(ii)State the activities on the critical path.[1]
  3. (a)(iii)State the minimum time to complete the opening of the new café.[1]
  4. (a)(iv)Calculate the free float of Activity F.[2]
  5. (b)Refer to your answers to 2(a) and any other information. Discuss whether PY's directors should be confident that the café in city X will be open in time for the summer season.[12]

This question uses a diagram from the original paper, which isn't shown here. Open the full paper from the past papers archive to see it.

Mark scheme

Marking points from the official mark scheme (Feb/Mar 2019). The mark or mark type is shown in brackets.

  1. [4] (a)(i) Node 3: EST = 2 LFT = 2; Node 4: EST = 4 LFT = 7
  2. [1] (a)(ii) ACEK
  3. [1] (a)(iii) 9 (weeks)
  4. [1] (a)(iv) Free float = EST of next activity – duration this activity – EST of this activity
  5. [1] (a)(iv) 5 – 3 – 2
  6. [2] (a)(iv) Free float F = 0 (weeks)
  7. [0] (b) Definition of network analysis: this is part of project management to ensure that resources are used efficiently. Also known as critical path analysis it identifies all tasks in a project, puts them in the correct sequence and allows for the identification of the critical path.
  8. [0] (b) Planning of when resources are needed and their use can save time
  9. [0] (b) Sets target to work towards
  10. [0] (b) Construction of network diagram forces managers to plan project carefully
  11. [0] (b) Identifies critical activities for management to focus on
  12. [0] (b) Figures are based on estimates / assumptions so could be unreliable
  13. [0] (b) Identifies whether new outlet can be opened in time for peak seasonal demand
  14. [0] (b) 9 weeks minimum time according to the CPA
  15. [0] (b) 1 week float
  16. [0] (b) Reference to specific critical activities / aspects of the network e.g. equipment must be delivered by week 6
  17. [0] (b) 75 cafes so have done this multiple times before
  18. [0] (b) Some activities depend on external factors such as ordering and delivery of equipment and building work
  19. [0] (b) Planning of when resources are needed help ensure project is more organised and therefore time is managed more effectively
  20. [0] (b) Targets set will help motivate staff and increase efficiency therefore more likely to be completed on time
  21. [0] (b) Construction of network diagram forces managers to plan project carefully and therefore coordinate resources such as HR, Operations and Finance
  22. [0] (b) Identifies critical activities for management to focus on. Thus, if critical activities are delayed managers can divert resources from non-critical activities to get project back on track
  23. [0] (b) Figures are based on estimates / assumptions so could be unreliable
  24. [0] (b) Network presented is relatively simplistic – more detail needed
  25. [0] (b) Doesn't guarantee that project will be completed on time
  26. [0] (b) PY has experience of opening many outlets so should be relatively accurate
  27. [0] (b) Needs to be managed effectively
  28. [0] (b) No control over external influences e.g. suppliers
  29. [0] (b) Not much margin for error as only one week float

Write your answer and get it marked

On Oracle Prep you can write or photograph your own answer and have it marked by AI against this mark scheme, with feedback on what you missed.

Sign up free →

About this question

Topic
Operations management, A-Level Business Studies (syllabus 9609). Structured question, 20 marks.
Source
A-Level Business Studies, Feb/Mar 2019 Paper 3 Variant 2, question 2.