Skip to main content
O-LevelPakistan StudiesThe environment of PakistanMay/June 2025 · Q325 Marks

(a) (i) Study Fig. 3.1, a map showing selected thermal power stations in southern and western Pakistan.

  1. (a)(i)Using Fig. 3.1 only, identify: – the city that is located close to a thermal power station in the west of Pakistan. ....................................................................................................................... – the number of thermal power stations located in Sindh. .......................................................................................................................[2]
  2. (a)(ii)Using Fig. 3.1 only, describe the distribution of thermal power stations.[3]
  3. (b)(i)Study Fig. 3.2, a diagram of a coal-fired thermal power station. Complete the labels on Fig. 3.2. Choose the correct words from the box and place them in the spaces provided. boiler cooling tower generator turbine[2]
  4. (b)(ii)Describe how coal is mined in an open cast mine.[2]
  5. (b)(iii)Cost is one factor that can affect the availability of electricity. State three other factors that can affect the availability of electricity in Pakistan.[3]
  6. (b)(iv)Explain why the cost of some non-renewable power sources in Pakistan may increase. You should develop your answer.[4]
  7. (c)(i)Define 'renewable energy'.[1]
  8. (c)(ii)Describe how electricity can be generated from geothermal resources.[2]
  9. (d)Read the following two views about ways to increase renewable power generation in Pakistan: A Pakistan should focus more on small-scale power generation such as solar panels in villages. B Pakistan should focus more on large-scale power-generation projects such as hydel dams. Which view do you agree with more? Give reasons to support your answer and refer to examples you have studied. You should consider view A and view B in your answer.[6]

This question uses a diagram from the original paper, which isn't shown here. Open the full paper from the past papers archive to see it.

Mark scheme

Marking points from the official mark scheme (May/June 2025). The mark or mark type is shown in brackets.

  1. [2] the city that is located close to a thermal power station in the west of Pakistan: Quetta
  2. the number of thermal power stations located in Sindh: 6
  3. 2 @ 1 mark
  4. [3] clustered/widespread/uneven
  5. in E/SE/S/central Pakistan
  6. most are in Sindh (and Punjab)/Sindh has the highest number of power stations
  7. more in Sindh than Punjab/Balochistan/KPK/more in Punjab than Balochistan/KPK
  8. around/near Karachi
  9. S/SE of Peshawar
  10. one/isolated power station in west/near/S/SSW of Quetta
  11. along/near/on/around rivers/Indus
  12. on/along boundaries between, e.g. Balochistan/Punjab/Sindh
  13. 2/3 are close to international boundaries
  14. 3 @ 1 mark
  15. [2] (Labels on diagram)
  16. boiler
  17. cooling tower
  18. generator
  19. turbine
  20. 3 or 4 correct = 2 marks
  21. 1 or 2 correct = 1 mark
  22. [2] drills are used to create holes in the rock/prepare the area
  23. the surface rocks are removed/explosives/blasting used
  24. excavators/machinery/power shovels used to remove overburden/rock/debris / to scoop up/dig out coal/mineral
  25. (coal/mineral) is loaded into / transported by lorries/trucks/railway wagons/trolleys/conveyors
  26. 2 @ 1 mark
  27. [3] topography/rugged terrain/mountains/deserts
  28. extreme temperatures/heavy rainfall/extreme climate
  29. flooding/high winds/(thunder)storms/earthquakes/landslides
  30. supply of, e.g. fossil fuels/coal/oil/gas/water/sunshine
  31. power stations/network/grid/power lines/pylons
  32. siltation in reservoirs/dams
  33. population density/demand/high usage
  34. industrialisation/industrial estates
  35. load shedding
  36. loss of electricity from (long) transmission lines
  37. workers/labour
  38. 3 @ 1 mark
  39. [4] scarcity/running out/limited supply of natural resources available in Pakistan; natural resources have to be imported
  40. need for higher quality minerals; which have higher value, increasing cost of energy produced
  41. natural resources have to be imported; causing higher transportation costs
  42. high(er) costs of imported minerals; due to currency depreciation/changes in exchange rates
  43. decreased production of natural resources in other countries; can affect global trade values (e.g. oil)
  44. higher costs of mineral extraction; technology/machinery/ skilled labour required
  45. costs of building/maintaining pylons/powerlines/pipelines; causes higher energy costs for consumers
  46. increased demand for power/growing population; demand higher than supply/competition increases prices
  47. political factors; increasing tariffs/taxes on natural resources/influence of international organisations (e.g. IMF/OPEC)
  48. Note: 1 mark for simple point and a further mark for the development of the point. 1 mark for second simple point and a further mark for development of the second point.
  49. Note: Max. 2 marks if no development.
  50. 2 @ 2 marks
  51. [1] Energy that can be reused/will not run out/is infinite
  52. 1 @ 1 mark
  53. [2] drill down to find/use areas of underground heat/hot water
  54. water is pumped down/heated by hot rocks/Earth's core
  55. water turns to steam/steam comes to the surface
  56. spins/turns/rotates/drives turbines/generator creates electricity
  57. 2 @ 1 mark
  58. [6] Levels marking
  59. No valid response
  60. Level 1
  61. Simple point referring to one view (1)
  62. Simple points referring to any view (2)
  63. Level 2
  64. Developed point referring to one view only (3)
  65. Developed points referring to both views or developed point and a relevant example (4)
  66. Level 3
  67. Developed points referring to both views with evaluation or relevant example (5)
  68. Developed points referring to both views with evaluation and relevant example (6)
  69. Content guide
  70. arguments for focusing on small-scale power generation such as solar panels in villages:
  71. small scale power generation can support households that don't have access to the national grid (around 25%)/in more remote areas to improve quality of life/access to education
  72. potential to generate electricity during load shedding
  73. relatively inexpensive, NGOs sometimes provide finance to set up such equipment
  74. arguments against focusing on small-scale power generation such as solar panels in villages:
  75. would not produce sufficient energy to meet future demand for domestic or industrial use, which could impact GDP
  76. equipment may still be too expensive for some households
  77. some power generation methods are not available 24/7
  78. batteries to store energy are extremely expensive
  79. arguments for focusing on large-scale power generation such as hydel dams:
  80. capacity to generate large amounts of energy which reduces reliance on imported fossil fuels, improving balance of trade
  81. can provide a more consistent supply of energy which is needed for industry/could reduce frequency of loadshedding
  82. large-scale construction projects can generate employment
  83. arguments against focusing on large-scale power generation such as hydel dams:
  84. hydel dams require a lot of land to be flooded for reservoir
  85. may require international experts to support, which can be expensive
  86. overall costs of large-scale projects are very high, which may mean investment in other areas/services is reduced

Write your answer and get it marked

On Oracle Prep you can write or photograph your own answer and have it marked by AI against this mark scheme, with feedback on what you missed.

Sign up free →

About this question

Topic
The environment of Pakistan, O-Level Pakistan Studies (syllabus 2059). Structured question, 25 marks.
Source
O-Level Pakistan Studies, May/June 2025 Variant 2, question 3.