A lift (elevator) of weight 13.0kN is connected by a cable to a motor, as shown in Fig. 2.1. [Figure 2.1] The lift is pulled up a vertical shaft by the cable. A constant frictional force of 2.0kN acts on the lift when it is moving. The variation with time t of the speed v of the lift is shown in Fig. 2.2. [Figure 2.2]
- (a)State what is meant by work done.[1]
- (b)(i) 1.the acceleration of the lift between time t = 0 and t = 3.0 s[2]
- (b)(i) 2.the work done by the motor to raise the lift between time t = 3.0s and t = 6.0s.[2]
- (b)(ii)The motor has an efficiency of 67%. The tension in the cable is 1.6 × 104 N at time t = 2.5 s. Determine the input power to the motor at this time.[3]
- (b)(iii)State and explain whether the increase in gravitational potential energy of the lift from time t = 0 to t = 7.0s is less than, the same as, or greater than the work done by the motor. A calculation is not required.[1]
This question uses a diagram from the original paper, which isn't shown here. Open the full paper from the past papers archive to see it.
Mark scheme
Marking points from the official mark scheme (Oct/Nov 2019). The mark or mark type is shown in brackets.
- [1] (work done =) force × distance moved in direction of force
- [1] acceleration = gradient or a = (v – u)/t or a = ∆v/t
- [1] e.g. a = 2.4/3.0 = 0.80 m s-2
- [1] tension in cable = (13.0 + 2.0) × 103
- [1] work done = 15 × 103 × (3.0 × 2.4) = 1.1 x 105 J
- [1] power = Fv
- [1] v = 2.0 (m s⁻¹)
- [1] input power = (1.6 × 104 × 2.0)/0.67 = 4.8 × 104 W
- [1] work is done against friction so (increase in) GPE is less (than work done by motor) or energy is lost or transferred or converted to heat/thermal energy due to friction or resistance force or work is done lifting the cable so GPE is less