A turbine at a hydroelectric power station is situated at a vertical distance of 30 m below the level of the surface of a large lake. The water passes through the turbine at a rate of 340 m³ per minute. The overall efficiency of the turbine and generator system is 90%. The density of water is 1000 kg m⁻³. What is the useful power output of the power station?

A0.15 MW
B1.5 MW
C1.7 MW
D90 MW

✓ Correct answer

B: 1.5 MW

Practise more questions on this topic

Oracle Prep sorts past-paper questions by topic, so you can drill Work, energy and power and see which topics are most likely to come up next.

Sign up free →

About this question

Topic
Work, energy and power, A-Level Physics (syllabus 9702). Multiple choice, 1 mark.
Source
A-Level Physics, Feb/Mar 2025 Paper 1 Variant 2, question 17.

Questions and mark schemes are from past examination papers and remain the copyright of the exam board. How Oracle Prep builds its content

Related Physics questions

© 2026 Oracle Prep