A company producing salt from sea water changed to a new process. The amount of salt obtained each week increased by 2% of the amount obtained in the preceding week. It is given that in the first week after the change the company obtained 8000 kg of salt.
- (i)Find the amount of salt obtained in the 12th week after the change.[3]
- (ii)Find the total amount of salt obtained in the first 12 weeks after the change.[2]
Mark scheme
Marking points from the official mark scheme (May/June 2018). The mark or mark type is shown in brackets.
- [B1] (i) r = 1.02 or 102/100 used in a GP in some way. Can be awarded here for use in Sn formula.
- [M1] (i) Use of ar^(n-1) with a = 8000 & n = 12 or with a = 8000/1.02 and n = 13.
- [A1] (i) Amount in 12th week = 8000(1.02)¹¹ = 9950 (kg) awrt. Note: Final answer of either 9943 or 9940 implies M1. Full marks can be awarded for a correct answer from a list of terms.
- [M1] (ii) Use of Sn with a = 8000 and n = 12 or addition of 12 terms. Total is 8000((their r)¹² - 1) / ((their r) - 1).
- [A1] (ii) = 107000 (kg) awrt. Correct answer but no working 2/2.