A crane is used to raise a block of mass 600kg vertically upwards at a constant speed through a height of 15 m. There is a resistance to the motion of the block, which the crane does 10000J of work to overcome.
- (a)Find the total work done by the crane.[2]
- (b)Given that the average power exerted by the crane is 12.5kW, find the total time for which the block is in motion.[2]
Mark scheme
Marking points from the official mark scheme (Feb/Mar 2022). The mark or mark type is shown in brackets.
- [M1] 600g × 15 [= 90 000] (Attempt potential energy.)
- [A1] Total work done by crane [90 000 + 10 000 =] 100 000 J
- [M1] 100 000 = 12 500 × t (Use of work done = power × time to set up an equation from which t can be found.)
- [A1 FT] Time = 8 s (FT on their work done = 100 000)