A-LevelBusiness StudiesOperations management9609/31 · May/June 2019 · Q221 Marks

Refer to Table 1.

  1. (a)Construct a network diagram, including the earliest start times (EST) and latest finishing times (LFT) of all the activities.[6]
  2. (b)(i)Calculate the following: minimum project duration[1]
  3. (b)(ii)Calculate the following: free float for activity D.[2]
  4. (c)BSJ currently has problems meeting deadlines for jewellery trade fairs (lines 36-42). Evaluate the usefulness of critical path analysis to BSJ in helping the company meet these deadlines.[12]

This question uses a diagram from the original paper, which isn't shown here. Open the full paper from the past papers archive to see it.

Mark scheme

Marking points from the official mark scheme (May/June 2019). The mark or mark type is shown in brackets.

  1. [2(a)] Reasonable attempt at network (no marks awardable for any of below) 2 mark
  2. [2(a)] All ESTs correct 2 marks
  3. [2(a)] 2 or more EST 1 mark
  4. [2(a)] 2 or more LFT 1 mark
  5. [2(a)] All LFTs correct 2 marks
  6. [2(a)] Activities in correct order 1 mark
  7. [2(a)] Nodes numbered 1 mark
  8. [2(b)(i)] 24 (weeks) 1 mark
  9. [2(b)(ii)] Free float = The amount of time that a scheduled activity can be delayed without delaying the earliest start time of any successor activity
  10. [2(b)(ii)] or EST next activity – duration – EST 1 mark
  11. [2(b)(ii)] = 22 – 2 – 13 = 7 weeks 2 marks
  12. [2(b)(ii)] Units must be stated
  13. [2(b)(ii)] 7 (1)
  14. [2(c) Knowledge] CPA enables project duration to be calculated so that key dates can be determined and activities planned
  15. [2(c) Knowledge] CPA enables start times of activities to be known so that appropriate resources can be assembled
  16. [2(c) Knowledge] CPA enables latest finish times to be known so that progress can be monitored and action taken if activities are not going to be in time
  17. [2(c) Knowledge] Critical path identified so managers focus on high priority activities
  18. [2(c) Knowledge] Knowing floats enables consequences of delays to be identified and resource allocation altered to minimise disruption to schedules
  19. [2(c) Knowledge] Reference to inability to meet deadline for jewellery fairs, jewellery
  20. [2(c) Application] Production, types of jewellery, need to save 4 weeks
  21. [2(c) Application] Reference to specific parts of the network e.g. duration of research and preparation of designs
  22. [2(c) Application] Reference to float of activity D
  23. [2(c) Application] Reference to specific critical activities
  24. [2(c) Application] Experience that BSJ has in preparing for trade fairs and existing data on timescales
  25. [2(c) Application] New designs for trade fairs
  26. [2(c) Analysis] Key dates can be determined and activities planned
  27. [2(c) Analysis] Appropriate resources can be assembled
  28. [2(c) Analysis] Progress can be monitored and action taken if activities are not going to be in time
  29. [2(c) Analysis] Managers are enabled focus on high priority activities increasing the chance of completion on time
  30. [2(c) Analysis] Consequences of delays can be identified and resource allocation altered to make sure jewellery is ready on time
  31. [2(c) Analysis] Each activity can be researched to see if any time can be saved
  32. [2(c) Analysis] Activities can be identified to save the 4 weeks needed
  33. [2(c) Evaluation] Technique only as good as data
  34. [2(c) Evaluation] Difficult to estimate activity durations
  35. [2(c) Evaluation] Past years may not be a good guide to next year - designs vary
  36. [2(c) Evaluation] CPA costs but is small compared to cost of project
  37. [2(c) Evaluation] Great value as makes Janice/Anil look closely at activities and could improve reputation and sales if appropriate changes implemented.

Write your answer and get it marked

On Oracle Prep you can write or photograph your own answer and have it marked by AI against this mark scheme, with feedback on what you missed.

Sign up free →

About this question

Topic
Operations management, A-Level Business Studies (syllabus 9609). Structured question, 21 marks.
Source
A-Level Business Studies, May/June 2019 Paper 3 Variant 1, question 2.