A manufacturing business provided the following information. | | $ | |:---|:---| | prime cost | 30 500 | | factory overheads | 17200 | | cost of goods produced | 46000 | | office and selling expenses | 9500 | | opening work-in-progress | 5 100 | What was the value of the closing work-in-progress?

A$1700
B$3400
C$6800
D$16300

✓ Correct answer

C: $6800