A manufacturer provided the following information. cost of raw materials consumed $20000 direct wages $10000 light and heat $5000 machinery repairs $3000 What was the prime cost?
This question uses a diagram from the original paper, which isn't shown here. Open the full paper from the past papers archive to see it.
✓ Correct answer
B: $30000