The times taken, in minutes, to complete a word processing task by 250 employees at a particular company are summarised in the table. Time taken (t minutes) 0 ≤ t < 20 | 20 ≤ t < 40 | 40 ≤ t < 50 | 50 ≤ t < 60 | 60 ≤ t < 100 Frequency 32 | 46 | 96 | 52 | 24
- (a)Draw a histogram to represent this information.[4]
- (b)From the data, the estimate of the mean time taken by these 250 employees is 43.2 minutes. Calculate an estimate for the standard deviation of these times.[3]
This question uses a diagram from the original paper, which isn't shown here. Open the full paper from the past papers archive to see it.
Mark scheme
Marking points from the official mark scheme (Oct/Nov 2022). The mark or mark type is shown in brackets.
- [M1] At least 4 frequency densities calculated (eg. fd = 32/20) (condone f/cw±0.5 if unsimplified), accept unsimplified, may be read from graph using their scale no lower than 1 cm = fd 1
- [A1] All bar heights correct on graph, using their suitable linear scale with at least 3 values indicated, no lower than 1 cm = fd 2.
- [B1] Bar ends at [0,] 20, 40, 50, 60, 100 (at axis), 5 bars drawn 0 < time axis < 100, linear scale with at least 3 values indicated.
- [B1] Axes labelled frequency density (fd), time (t) and minutes (mins, m) or appropriate title. (Axes may be reversed).
- [B1] Midpoints 10 30 45 55 80 At least 4 correct midpoints seen (check data table).
- [M1] Appropriate variance formula with their 5 midpoints (not upper bound, lower bound, class width, frequency density, frequency or cumulative frequency). Condone 1 frequency error. If correct midpoints seen accept [32×10² + 46×30² + 96×45² + 52×55² + 24×80² / 250 - {43.2² or 1866.24} ].
- [A1] www, final answer 18.25814887 to at least 3SF. If M0 earned SC B1 for final answer 18.25814887 to at least 3SF.