The table shows the expected costs and benefits from four government projects. The government can afford only one project. Which project should the government choose? | | private benefits (m) | external benefits (m) | private costs (m) | external costs (m) | |---|---|---|---|---| | A | 40 | 200 | 60 | 70 | | B | 60 | 160 | 100 | 20 | | C | 100 | 210 | 100 | 120 | | D | 150 | 90 | 120 | 140 |

Mark scheme

Marking points from the official mark scheme (May/June 2017). The mark or mark type is shown in brackets.

  1. [1] A

Write your answer and get it marked

On Oracle Prep you can write or photograph your own answer and have it marked by AI against this mark scheme, with feedback on what you missed.

Sign up free →

About this question

Topic
Government microeconomic intervention, A-Level Economics (syllabus 9708). Structured question, 1 mark.
Source
A-Level Economics, May/June 2017 Paper 3 Variant 1, question 3.

Questions and mark schemes are from past examination papers and remain the copyright of the exam board. How Oracle Prep builds its content

Related Economics questions

© 2026 Oracle Prep