A cost-benefit analysis is carried out on the construction of a hydroelectric power station. Which combination of circumstances would be most likely to lead to the scheme being approved?

  1. A cost-benefit analysis is carried out on the construction of a hydroelectric power station. Which combination of circumstances would be most likely to lead to the scheme being approved? A Private benefits are greater than private costs. B Social benefits are greater than social costs. C Social benefits are greater than total costs. D Total costs are greater than total revenue.[1]

Mark scheme

Marking points from the official mark scheme (Oct/Nov 2018). The mark or mark type is shown in brackets.

  1. [1] B

Write your answer and get it marked

On Oracle Prep you can write or photograph your own answer and have it marked by AI against this mark scheme, with feedback on what you missed.

Sign up free →

About this question

Topic
Government microeconomic intervention, A-Level Economics (syllabus 9708). Structured question, 1 mark.
Source
A-Level Economics, Oct/Nov 2018 Paper 3 Variant 2, question 2.

Questions and mark schemes are from past examination papers and remain the copyright of the exam board. How Oracle Prep builds its content