(a) Refer to the network diagram in Fig. 1 (copied below) and to Table 1 in the Insert. [Figure 1]
- (a)(i)Complete the network diagram at node 2.[2]
- (a)(ii)Calculate the free float of activity E.[3]
- (a)(iii)Calculate the total float of activity G.[3]
- (b)Evaluate whether the Operations Manager is right to be confident that the new machines will be ready for production within the 14-day deadline.[12]
This question uses a diagram from the original paper, which isn't shown here. Open the full paper from the past papers archive to see it.
Mark scheme
Marking points from the official mark scheme (Oct/Nov 2022). The mark or mark type is shown in brackets.
- [1] (a)(i) EST = 2
- [1] (a)(i) LFT = 5
- [1] (a)(ii) Free float is the maximum time an activity can be delayed without delaying the next activity.
- [1] (a)(ii) = EST next activity – duration – EST
- [2] (a)(ii) = 8 – 3 – 2
- [3] (a)(ii) = 3 days
- [1] (a)(iii) Total float is the maximum time an activity can be delayed without delaying the whole project
- [1] (a)(iii) = LFT - duration – EST
- [2] (a)(iii) = 10 – 1 – 0
- [3] (a)(iii) = 9 days
- [K] (b) Definition of network analysis: this is part of project management to ensure that resources are used efficiently. Also known as critical path analysis it identifies all tasks in a project, puts them in the correct sequence and allows for the identification of the critical path.
- [K] (b) Understanding of role of CPA in planning: Planning of when resources are needed: CPA sets out order and times of activities.
- [K] (b) Understanding of role of CPA in planning: CPA sets out earliest start and latest finish times and gives critical path.
- [K] (b) Understanding of role of CPA in planning: Sets target to work towards.
- [K] (b) Understanding of role of CPA in planning: Construction of network diagram forces managers to plan project carefully.
- [K] (b) Understanding of role of CPA in planning: Identifies critical activities for management to focus on.
- [K] (b) Understanding of role of CPA in planning: Knowledge of free and total float.
- [K] (b) Understanding of role of CPA in planning: Definitions of rationalisation, sub-contracting, outsourcing.
- [K] (b) Understanding of role of CPA in planning: CPA enables decisions on how to minimise chance of delays.
- [App] (b) New machines to replace two production lines.
- [App] (b) First time the manager has used CPA.
- [App] (b) Use of data from the network diagram.
- [App] (b) Suppliers provided information and are responsible for activities B–J.
- [App] (b) AP's objectives are lower costs and increased capacity.
- [App] (b) Use of data from 2a – 14 days forecast minimum duration.
- [App] (b) AP workers are unskilled (the training activity may take longer than expected).
- [An] (b) CPA is a quantitative technique that gives accuracy to forecasting timescale, therefore making it more likely that the machines will be ready on time.
- [An] (b) CPA enables resources to be given to activities at optimum time, avoiding idle resources and possibility of loss or damage.
- [An] (b) Knowing the critical path enables focus on completion of key activities.
- [An] (b) Consideration of possible variations in the network e.g. the allocated activity times might be over/under estimated, could training and testing be run together to save time?
- [Eval] (b) Justified conclusion regarding confidence of operations manager as it is first time with CPA.
- [Eval] (b) If AP has contributed to the information and planning the confidence is enhanced.
- [Eval] (b) Accuracy of duration relies on supplier carrying out B–J on time, to what extent does AP have confidence?
- [Eval] (b) Has the operations manager discussed the importance of these accuracy levels with the supplier?
- [Eval] (b) The network diagram may not be accurate, especially as it a first-time effort.
- [Eval] (b) CPA, even if well done, does not guarantee times being met, or duration being shortened.
- [Eval] (b) Lack of contingency time means any delay at all will result in missing the 14-day deadline unless additional relevant resources are available.
- [Eval] (b) External factors e.g. late delivery of resources might mean duration is longer.