A-LevelBusiness StudiesOperations management9609/31 · Oct/Nov 2018 · Q217 Marks

Refer to Table 1. Calculate:

  1. (a)(i)difference in capacity utilisation between forecast production in the first six months and the most efficient level[3]
  2. (a)(ii)change in monthly total cost between forecast production in the first six months and the most efficient level of production.[2]
  3. (b)Refer to your results to 2(a) and any other information. Discuss the value of implementing ERP in the new factory.[12]

Mark scheme

Marking points from the official mark scheme (Oct/Nov 2018). The mark or mark type is shown in brackets.

  1. [1] (a)(i) Capacity utilisation = Current output / Maximum output × 100
  2. [1] (a)(i) Current = 100/300 × 100 = 33.3%
  3. [1] (a)(i) Most efficient = 260/300 × 100 = 86.7%
  4. [3] (a)(i) Difference 53.4% or rounded 87% -33% = 54%
  5. [3] (a)(i) % change 53.4/33.3 × 100 = 160.3%
  6. [2] (a)(i) Other possible route: 160/300 × 100 = 53.3%. Note: Do not reward 160 on its own. No % then 2 marks
  7. [1] (a)(ii) TC current = $3.20 × 100 = $320 000 per month
  8. [1] (a)(ii) TC most efficient = $2.20 × 260 = $572 000
  9. [2] (a)(ii) Change = $252 000 per month (000s and $ required)
  10. [2] (a)(ii) % change = 78.75%
  11. [1] (a)(ii) Total cost change between first six months and most efficient level = $1512 000
  12. [1] (a)(ii) Deduct 1 mark for errors – no 000s and/or $. Answer of 252 or $252 or 252 000
  13. [K] (b) ERP - The use of a single computer application to plan the purchase and use of resources in an organisation to improve the efficiency of operations or similar
  14. [K] (b) Role of ERP in reducing unit cost
  15. [K] (b) Link between ERP and lean production methods
  16. [K] (b) Role of ERP in enabling higher sales and capacity utilisation
  17. [K] (b) ERP is using dedicated software to integrate orders, materials, labour
  18. [K] (b) Role of ERP in supply chain management leading to improved customer service and competitive advantage
  19. [K] (b) ERP set up costs are high
  20. [APP] (b) SU assemble and manufacture – complex requirements suited to ERP
  21. [APP] (b) Delivery time important factor for customers
  22. [APP] (b) Range of umbrella products makes for complex inventory decisions
  23. [APP] (b) New factory is opportunity for new IT
  24. [APP] (b) Reasonable use of Table 1 data
  25. [AN] (b) Might enable quick decisions on marginally priced orders maintaining sales
  26. [AN] (b) Reduces cost of ordering and holding inventory
  27. [AN] (b) All departments can access same information improving communication issues
  28. [AN] (b) Enables rapid response to change and customised pricing
  29. [AN] (b) New factory and production methods ties in with new ERP opportunity
  30. [AN] (b) ERP expensive therefore impact on profits
  31. [AN] (b) Effectiveness relies on correct setting up and operation – training required
  32. [AN] (b) Requires accurate reliable information from suppliers and customers
  33. [EVAL] (b) Weighing up benefits and limitations (such as cost)
  34. [EVAL] (b) Does not guarantee lower costs – the human factor might intervene
  35. [EVAL] (b) Consideration of requirements for success, such as skills of operator or accuracy of information input.
  36. [EVAL] (b) Is planned ERP a full complete system or a partial one?
  37. [EVAL] (b) Consideration of relative importance of other factors

Write your answer and get it marked

On Oracle Prep you can write or photograph your own answer and have it marked by AI against this mark scheme, with feedback on what you missed.

Sign up free →

About this question

Topic
Operations management, A-Level Business Studies (syllabus 9609). Structured question, 17 marks.
Source
A-Level Business Studies, Oct/Nov 2018 Paper 3 Variant 1, question 2.