Refer to Appendix 1. Calculate: earliest start time (EST) for Activity F
- (a)(i)Refer to Appendix 1. Calculate: earliest start time (EST) for Activity F[2]
- (a)(ii)total float for Activity D[3]
- (a)(iii)free float for Activity C.[3]
- (b)Assess the role of critical path analysis (CPA) in the successful installation of the new coffee roasting machines.[12]
This question uses a diagram from the original paper, which isn't shown here. Open the full paper from the past papers archive to see it.
Mark scheme
Marking points from the official mark scheme (May/June 2021). The mark or mark type is shown in brackets.
- [1] Some attempt at identifying EST, e.g. additions of previous EST or definition
- [1] EST = 18 + 3
- [2] EST = 21 days
- [1] Definition - Total float is max. time an activity can be delayed without delaying the whole project (if no relevant equation or calculation)
- [1] LFT - duration – EST
- [2] Total float = 21 – 2 – 0
- [3] = 19 days
- [1] Definition - Free float is max. time an activity can be delayed without delaying the next activity (if no relevant equation or calculation)
- [1] EST next activity – duration – EST
- [2] Free float = 18 – 6 – 0
- [3] = 12 days
- Knowledge: Definition of network analysis: this is part of project management to ensure that resources are used efficiently. Also known as critical path analysis it identifies all tasks in a project, puts them in the correct sequence and allows for the identification of the critical path.
- Knowledge: Critical path identified so managers focus on high priority activities.
- Knowledge: Key dates can be determined, and activities planned.
- Knowledge: Appropriate resources can be assembled.
- Knowledge: Progress can be monitored.
- Knowledge: Gives workforce a guide so that finishing date can be met.
- Knowledge: Managers are enabled to focus on high priority activities.
- Application: Reference to more efficient faster coffee roasters, enabling over capacity at current production levels.
- Application: Ideas for expansion (open cafes) rely on greater coffee production.
- Application: Inexperienced new production manager has provided the information for the CPA.
- Application: Impact of installation on current production.
- Application: Marketing plan timing following installation (planned for one week after).
- Application: Use of data in Appendix 1: Minimum time of 28 days – Peter has set a deadline of one month.
- Application: Use of data in Appendix 1: Non-critical activities B, C, D, G
- Application: Use of data in Appendix 1: Critical path AEFH
- Analysis: CPA enables project duration to be calculated so that key dates can be determined, and activities planned.
- Analysis: CPA enables start times of activities to be known so that appropriate resources can be assembled.
- Analysis: CPA enables latest finish times to be known so that progress can be monitored, and action taken if activities are not going to be on time.
- Analysis: Knowing floats enables consequences of delays to be identified and resource allocation altered to minimise disruption to schedules.
- Analysis: Consequences of delays can be identified, and resource allocation altered to make sure roasters are ready on time.
- Analysis: CPA could set (unrealistic) targets that workers in striving to meet result in errors and mistakes in installation
- Evaluation: Technique only as good as data – would production manager be best person for collating this information?
- Evaluation: Difficulty of estimating activity durations – has contractor any input?
- Evaluation: CPA costs but is small compared to cost of project.
- Evaluation: Is CPA worthwhile for such a small simple project?