Refer to Table 3 and Appendix 1:
- (a)(i)Complete nodes 3 and 4 on the network analysis below (reproduced from the Insert).[4]
- (a)(ii)Identify the critical path. Write your answer below.[1]
- (a)(iii)Calculate the minimum time to complete the project to open Alderly Gardens. Write your answer below.[1]
- (a)(iv)Calculate the total float of Activity J.[2]
- (b)Evaluate the usefulness of network analysis to HBG when making operational decisions.[12]
This question uses a diagram from the original paper, which isn't shown here. Open the full paper from the past papers archive to see it.
Mark scheme
Marking points from the official mark scheme (May/June 2020). The mark or mark type is shown in brackets.
- [4] (a)(i) Node 3: EST = 5 (1 mark) LFT = 5 (1 mark) Node 4: EST = 6 (1 mark) LFT = 18 (1 mark)
- [1] (a)(ii) ACDEG (1 mark)
- [1] (a)(iii) 20 weeks (1 mark)
- [2] (a)(iv) Total float = LFT – duration – EST (1 mark) Or LST – EST (1 mark) 17-2-9=6 weeks (2 marks)
- [Knowledge] (b) Definition of network analysis: this is part of project management to ensure that resources are used efficiently. Also known as critical path analysis it identifies all tasks in a project, puts them in the correct sequence and allows for the identification of the critical path - fastest route to completion.
- [Analysis] (b) Planning of when resources are needed and their use can save time and money
- [Analysis] (b) Sets target to work towards
- [Analysis] (b) Construction of network diagram forces managers to plan project carefully
- [Analysis] (b) Identifies critical activities for management to focus on
- [Analysis] (b) Fixtures and fittings can be ordered to arrive just in time for their installation in week 18 so cash outflows can be delayed.
- [Analysis] (b) Targets set will help motivate staff and increase efficiency
- [Application] (b) Reference to activities in Table 3
- [Application] (b) Reference to total float / free float of individual activities
- [Application] (b) Reference to three spare weeks to complete project before the 23 week deadline
- [Evaluation] (b) Will need to be supported by other techniques such as Gantt charts to manage resources effectively
- [Evaluation] (b) Network presented is relatively simplistic – more detail needed
- [Evaluation] (b) Doesn't guarantee that project will be completed on time
- [Evaluation] (b) HBG has experience of planning building work so should be relatively accurate