A-LevelBusiness StudiesOperations management9609/32 · May/June 2020 · Q420 Marks

Refer to Table 3 and Appendix 1:

  1. (a)(i)Complete nodes 3 and 4 on the network analysis below (reproduced from the Insert).[4]
  2. (a)(ii)Identify the critical path. Write your answer below.[1]
  3. (a)(iii)Calculate the minimum time to complete the project to open Alderly Gardens. Write your answer below.[1]
  4. (a)(iv)Calculate the total float of Activity J.[2]
  5. (b)Evaluate the usefulness of network analysis to HBG when making operational decisions.[12]

This question uses a diagram from the original paper, which isn't shown here. Open the full paper from the past papers archive to see it.

Mark scheme

Marking points from the official mark scheme (May/June 2020). The mark or mark type is shown in brackets.

  1. [4] (a)(i) Node 3: EST = 5 (1 mark) LFT = 5 (1 mark) Node 4: EST = 6 (1 mark) LFT = 18 (1 mark)
  2. [1] (a)(ii) ACDEG (1 mark)
  3. [1] (a)(iii) 20 weeks (1 mark)
  4. [2] (a)(iv) Total float = LFT – duration – EST (1 mark) Or LST – EST (1 mark) 17-2-9=6 weeks (2 marks)
  5. [Knowledge] (b) Definition of network analysis: this is part of project management to ensure that resources are used efficiently. Also known as critical path analysis it identifies all tasks in a project, puts them in the correct sequence and allows for the identification of the critical path - fastest route to completion.
  6. [Analysis] (b) Planning of when resources are needed and their use can save time and money
  7. [Analysis] (b) Sets target to work towards
  8. [Analysis] (b) Construction of network diagram forces managers to plan project carefully
  9. [Analysis] (b) Identifies critical activities for management to focus on
  10. [Analysis] (b) Fixtures and fittings can be ordered to arrive just in time for their installation in week 18 so cash outflows can be delayed.
  11. [Analysis] (b) Targets set will help motivate staff and increase efficiency
  12. [Application] (b) Reference to activities in Table 3
  13. [Application] (b) Reference to total float / free float of individual activities
  14. [Application] (b) Reference to three spare weeks to complete project before the 23 week deadline
  15. [Evaluation] (b) Will need to be supported by other techniques such as Gantt charts to manage resources effectively
  16. [Evaluation] (b) Network presented is relatively simplistic – more detail needed
  17. [Evaluation] (b) Doesn't guarantee that project will be completed on time
  18. [Evaluation] (b) HBG has experience of planning building work so should be relatively accurate

Write your answer and get it marked

On Oracle Prep you can write or photograph your own answer and have it marked by AI against this mark scheme, with feedback on what you missed.

Sign up free →

About this question

Topic
Operations management, A-Level Business Studies (syllabus 9609). Structured question, 20 marks.
Source
A-Level Business Studies, May/June 2020 Paper 3 Variant 2, question 4.

Questions and mark schemes are from past examination papers and remain the copyright of the exam board. How Oracle Prep builds its content