A company has recently introduced a system of budgetary control. Workers have given the following reasons for materials costs being more than budgeted. 1 Budgeted material costs are incorrect. 2 Production machinery is outdated and wastes materials. 3 The company should purchase better quality materials to reduce wastage. Which reasons will cause actual material costs to be different from the budgeted costs?
✓ Correct answer
A: 1, 2 and 3