The following data were available for a department for July. [Table with 'budget' and 'actual' for 'direct labour hours' (40000, 41950), 'machine hours' (60000, 60900), 'overheads' ($480000, $499200)] What was the over or under absorption of overheads for July?
✓ Correct answer
D: $12000 under absorbed