A business absorbs overheads based on machine hours. During the last quarter it had the following budgeted and actual results. Actual overheads $118505; actual machine hours 6230; budgeted overheads $126725; budgeted machine hours 6850. By how much were overheads over or under absorbed?
✓ Correct answer
C: under absorbed by $3250