A-LevelAccountingCosting for materials and labour9706/12 · May/June 2016 · Q271 Mark

A business provided the following information for the past two months. month number of labour hours total overheads $ February 64000 918000 March 76000 1062000 What was the monthly fixed overhead cost?

A$144000
B$150000
C$768000
D$912000

✓ Correct answer

B: $150000

Practise more questions on this topic

Oracle Prep sorts past-paper questions by topic, so you can drill Costing for materials and labour and see which topics are most likely to come up next.

Sign up free →

About this question

Topic
Costing for materials and labour, A-Level Accounting (syllabus 9706). Multiple choice, 1 mark.
Source
A-Level Accounting, May/June 2016 Paper 1 Variant 2, question 27.