A business has the following budgeted and actual results for a period. $ budgeted fixed overheads 354 000 actual fixed overheads 360 000 under-absorption of overheads 3000 The fixed overheads are absorbed per unit. The budgeted number of units were 118000. What is the actual level of activity in units?
✓ Correct answer
B: 119000