The following information is available about two products. Product 1 per unit: material X 2 kilos, material Y 3 kilos, direct labour 3 hours. Product 2 per unit: material X 4 kilos, material Y 1 kilo, direct labour 6 hours. Production is planned to be 100 units of each product. 700 kilos of material X and 400 kilos of material Y are available. A total of 800 direct labour hours can be worked. What are the limiting factors?
✓ Correct answer
A: direct labour only