A business has two production departments: assembly and machinery. The following budgeted information is available. | | assembly | machinery | |:---|:---|:---| | labour hours | 5600 | 1350 | | machine hours | 1200 | 6900 | | overheads | $75000 | $80 000 | What is the overhead absorption rate for the assembly department?
✓ Correct answer
A: $13.39 per labour hour