A-LevelAccountingTraditional costing methods9706/12 · Feb/Mar 2023 · Q261 Mark

A manufacturing business makes a single type of product. It has two production departments, machining and assembly. A maintenance department provides services to the production departments. Budgeted figures for these departments are shown. overheads machining $800 000 assembly $400 000 maintenance $300 000 production units 200 000 50 000 The business uses a cost per unit rate to absorb overheads. Maintenance department overheads are transferred to production departments in proportion to output. Which figures are correct for the machining department?

Aoverheads $950 000 cost per unit $4.75
Boverheads $1000 000 cost per unit $5.00
Coverheads $1040 000 cost per unit $4.16
Doverheads $1040 000 cost per unit $5.20

✓ Correct answer

D: overheads $1040 000 cost per unit $5.20

Practise more questions on this topic

Oracle Prep sorts past-paper questions by topic, so you can drill Traditional costing methods and see which topics are most likely to come up next.

Sign up free →

About this question

Topic
Traditional costing methods, A-Level Accounting (syllabus 9706). Multiple choice, 1 mark.
Source
A-Level Accounting, Feb/Mar 2023 Paper 1 Variant 2, question 26.

Questions and mark schemes are from past examination papers and remain the copyright of the exam board. How Oracle Prep builds its content

Related Accounting questions

© 2026 Oracle Prep